Gantt Chart Maker
Make a Gantt chart online: list tasks with durations, dependencies and sections, see the computed dates, and download the chart as SVG or PNG.
Tasks
A task starts on its own start date, or the day after the task it follows finishes (whichever is later), or on the project start. Give an end date instead of a duration if you prefer; the end date is the task's last day. A section name starts a new group at that task.
The plan runs from Mon, Oct 5, 2026 to Tue, Oct 27, 2026, 23 calendar days in all.
| Task | Start | Finish | Calendar days | Working days |
|---|---|---|---|---|
| Research | Mon, Oct 5, 2026 | Wed, Oct 7, 2026 | 3 | 3 |
| Write the brief | Thu, Oct 8, 2026 | Fri, Oct 9, 2026 | 2 | 2 |
| Design | Sat, Oct 10, 2026 | Wed, Oct 14, 2026 | 5 | 3 |
| Development | Thu, Oct 15, 2026 | Thu, Oct 22, 2026 | 8 | 6 |
| Testing | Fri, Oct 23, 2026 | Mon, Oct 26, 2026 | 4 | 2 |
| Release | Tue, Oct 27, 2026 | Tue, Oct 27, 2026 | 1 | 1 |
Mermaid code
gantt
title Website launch plan
dateFormat YYYY-MM-DD
axisFormat %b %d
todayMarker off
section Planning
Research :2026-10-05, 2026-10-08
Write the brief :2026-10-08, 2026-10-10
section Build
Design :2026-10-10, 2026-10-15
Development :2026-10-15, 2026-10-23
section Launch
Testing :2026-10-23, 2026-10-27
Release :2026-10-27, 2026-10-28What Gantt Chart Maker Does
This Gantt chart maker takes a list of tasks and draws one bar for each, grouped into sections. Give each task a name and a duration in days, say which earlier task it follows, and the tool works out the start and finish dates. A table under the controls shows every date, and the chart is drawn from the same numbers, so the two always agree.
The dates are worked out by this page and written into the Mermaid code as explicit start and end dates. That is a deliberate choice. It lets the weekend option and the dependency rule behave exactly as described here, and it means the copied code draws the same chart wherever you paste it. The chart downloads as SVG or PNG.
How to Use Gantt Chart Maker
- Enter a chart title and the project start date
- Fill in the first task: a name and a duration in days
- Add more tasks, and use Starts after to chain each one to the task it follows
- Optionally give a task its own start date, an end date, or a section name
- Tick Skip weekends if durations should count working days, then check the table and chart
- Press Download SVG, Download PNG or copy the Mermaid code
Formula Used by Gantt Chart Maker
Finish date of a task
Last day = start day + (duration − 1) days
- start day
- The first day of the task, which counts as day one
- duration
- Length in whole days
Worked example
A 3-day task that starts on October 5, 2026.
- Day one is October 5
- Day two is October 6
- Day three is October 7
Result: The task finishes on October 7, and a task that follows it starts on October 8.
Finish date when weekends are skipped
Count the duration in Monday to Friday days, starting from the first working day on or after the start
- first working day
- The start day if it is a weekday, otherwise the next Monday
Worked example
An 8-day task that would start on Saturday, October 17, 2026, with weekends skipped.
- The start moves to Monday, October 19
- Working days: Oct 19, 20, 21, 22, 23 (5 days)
- Then Oct 26, 27, 28 (3 more days, 8 in all)
Result: The task runs from October 19 to October 28, which is 10 calendar days and 8 working days.
The example plan, with and without skipping weekends
Six tasks chained one after another from a Monday, October 5, 2026 start. Dates are first day to last day, as worked out by this tool.
| Task | Duration | Calendar days | Weekends skipped |
|---|---|---|---|
| Research | 3 days | Oct 5 – Oct 7 | Oct 5 – Oct 7 |
| Write the brief | 2 days | Oct 8 – Oct 9 | Oct 8 – Oct 9 |
| Design | 5 days | Oct 10 – Oct 14 | Oct 12 – Oct 16 |
| Development | 8 days | Oct 15 – Oct 22 | Oct 19 – Oct 28 |
| Testing | 4 days | Oct 23 – Oct 26 | Oct 29 – Nov 3 |
| Release | 1 day | Oct 27 | Nov 4 |
How to Read Your Result
Start date, dependency and project start
A task starts on the later of its own start date and the day after the task it follows finishes. With neither, it starts on the project start date. A task with an end date uses that date as its last day and ignores the duration box.
Why only earlier tasks can be followed
The Starts after menu lists only the tasks above the current one. That makes a loop, where A waits for B and B waits for A, impossible to enter. To make a task follow one that sits lower in the list, add the tasks in the order they happen.
What a problem does
A task with an invalid date, a duration that is not a whole number, or a dependency on a task with a problem is reported by number and left out of the chart. The other tasks are still drawn, so a typo in one row does not blank the whole plan.
Limitations & Accuracy Notes
- Weekends are Saturday and Sunday. Public holidays and company days off are not known, so move any task that crosses one by hand.
- With weekends skipped, the bars are still drawn across the weekend columns of the time axis. A task that spans a weekend looks longer than its working-day count.
- Durations are whole days. Hours, half days and milestones are not supported.
- There is no percent complete, resource assignment or critical path. The chart shows planned dates only.
- Dates must be between 1900 and 2200, a task can run up to 3,650 days, and a chart holds up to 60 tasks.
- Nothing is saved between visits. Copy the Mermaid code if you want to keep the chart.
Frequently Asked Questions
How do I make a Gantt chart online?
Set a project start date, then add one task per card with a name and a duration in days. Each task starts the day after the one it follows, so a chain of tasks lines up on its own. The chart and a table of start and finish dates update as you type, and you can download the chart as SVG or PNG.
How is the end date of a task worked out?
The start day counts as day one. A 3-day task that starts on October 5 runs October 5, 6 and 7 and finishes on October 7. The next task that follows it starts on October 8. If you enter an end date instead, that date is the task’s last day.
How do task dependencies work here?
Choose a task from the Starts after menu and the new task begins the day after that one finishes. If you also type a start date, the later of the two dates is used. You can only pick a task listed above, which rules out loops. A task with a problem is left out, and so are the tasks that follow it.
Can the chart skip weekends?
Yes. Tick Skip weekends and durations count Monday to Friday only, so a 5-day task takes one working week. A start on a Saturday or Sunday moves to Monday. The bars are still drawn across the weekend columns, and the tool does not know about public holidays, so move those tasks by hand.
Can I use an end date instead of a duration?
Yes. Fill in the End date field and the duration box is ignored for that task. The end date is the last day of the task and cannot come before the start. With weekends skipped, an end date that falls on a Saturday or Sunday counts as the Friday before it.
Does the chart show the critical path or progress?
No. It draws one bar per task from its start and finish dates, grouped into sections, and shows the dates in a table. It has no percent complete, resource assignments or critical path calculation. For a small plan or a slide, that is often enough. For live tracking, use a project management tool.
How do I export the Gantt chart?
Use Download SVG for a sharp vector file, or Download PNG for an image drawn at 2x on a white background. The Mermaid code is shown below the chart with a copy button, and every task carries explicit dates, so it draws the same wherever you paste it. Nothing is saved between visits.
References & Further Reading
- Mermaid — Gantt diagrams — Task syntax: a title, a colon, then a start and an end date or a duration; sections; the excludes option
- Mermaid — About Mermaid — What Mermaid is and how it draws diagrams from text